education.vic.gov.au

School operations

Cooling Towers

4. Audit of risk management plan

The principal and/or their delegate must ensure that:

  • the risk management plan is independently audited on a yearly basis as part of the annual independent audit of cooling tower system management
  • a review of the risk management plan is performed on a yearly basis
  • the audit and review is scheduled on the OHS activities calendar (XLSX)External Link
  • the risk management plan be made available to an authorised officer of the Department of Health and Human Services on request.
Chapter 4 of the Cooling Towers Procedure on auditing requirements associated with the cooling tower risk management plan

Reviewed 06 September 2022

Was this page helpful?